1. IE browser is NOT supported anymore. Please use Chrome, Firefox or Edge instead.
2. If you are a new user, please register to get an IHEP SSO account through https://login.ihep.ac.cn/registlight.jsp Any questions, please email us at helpdesk@ihep.ac.cn or call 88236855.
3. If you need to create a conference in the "Conferences, Workshops and Events" zone, please email us at helpdesk@ihep.ac.cn.
4. The max file size allowed for upload is 100 Mb.
4–7 Jun 2018
IHEP
Asia/Shanghai timezone
Young Engineers are encouraged to attend the open courses in 4th June. You can sign up when registering.

Reliability and management strategy of the cryogenic and utility systems for SRF test facility at the RISP

Not scheduled
15m
Main building (IHEP)

Main building

IHEP

Beijing

Speaker

Mr KI WOONG LEE (Institute for Basic Science)

Description

Superconducting radio frequency test facility, cryogenic system, cryomodule, cavity, maintenance, helium leak

Summary

The Rare Isotope Science Project (RISP) had completed the installation of the cryogenic system at the Superconducting Radio Frequency Test Facility (SRF TF) in June 2016. The commissioning was successfully completed for 6 months. The TF is being used in order to test SRF cavities, cryomodules and SC magnets which will be applied to RISP’s accelerator. In 2017, the performance tests of cryomodules, superconducting cavities, superconducting magnet and SCL demo were conducted 18 times. We have experienced numerous trials and gotten the know-how at cryogenic systems for performance tests. This presentation introduces the problems that occurred in cryogenic and utility systems of the SRF TF during the performance tests and how the systems are modified and maintained. Causes of the problems are analyzed and solutions that we find out are applied to the SRF TF. The current status are presented and management process of the SRF TF are discussed in order to operate that efficiently and safely. In addition, helium inventory and management method are introduced. Our management process that we set up to increase reliability and maintainability will be applied to new SRF TF.

Primary author

Mr KI WOONG LEE (Institute for Basic Science)

Co-authors

Dr HEE CHUL PARK (Institute for Basic Science) Dr HYUN CHUL Jo (Institute for Basic Science) Dr HYUN MAN JANG (Institute for Basic Science) Mr JAE HEE SHIN (Institute for Basic Science) Mr SUNGWOON YOON (Institute for Basic Science) Dr TAE KYUNG KI (Institute for Basic Science)