- OTP needs to be updated
 
	- Schedule
 
	- Sensor: 3 months delay
 
	- pre-production ASIC probing:  ID 254 end of April   3.5
 
	- PEB: FDR in May
	
		-     Jie: some of procument component are not ready
 
	
	 
	- HV: payment of pre-prod: Shandong will pay 
 
	- Module: 
	
		- Polymide who pay: need to clarify
		
			- Joao: should not pay items not in MOU
 
		
		 
		- Module flex: pre-prod finish in end of May, most likely to delay
 
		- Module assembly in July
 
		- Database: need double check whether the database works
		
			-     Mei will introduce sensor database
 
		
		 
	
	 
	- DU:
	
		- Joao: needs to know Didier's method     
 
		- try to finish earlier
 
		- manpower to CERN needed from Oct 20205 to end of 2028
 
	
	 
     3. ASIC probing update    
     4. Plan for moving to new clean room
	- Joao: need more details from Yunyun
 
             
            
                
                    There are minutes attached to this event.
                    